Completed in 2016, renovations to the Tucson Convention Center include new locker rooms, sound and video system, renovated bathrooms, lighting and interior wall upgrades, new press box, weight room facilities, concession stand and seat upgrades. These upgrades assisted in bringing the Roadrunners Hockey team and new arena football, Tucson Sugar Skulls, to Tucson, which has enjoyed a warm reception.

In the November 2018 Board meeting, the Rio Nuevo Board  approved a $2.2M replacement of the arena’s ice plant and floor to replace the currently antiquated system.

At the March 2019 Rio Nuevo meeting, the Board voted to proceed with a 350-spot parking garage east of the Tucson Convention Center. The district will pay $292,000 for a garage design and help in creating a request for proposal to solicit bids to build it. Construction could begin in 2020, with work planned around the schedules of the Tucson Sugar Skulls and Tucson Roadrunners, the football and hockey teams that share the Convention Center Arena.

At the August 2019 Rio Nuevo special meeting the Board unanimously approved a list of priorities for a $65 million renovation plan for the Tucson Convention Center. The package of improvements, upgrades and additions throughout the Convention Center campus includes work on the main convention complex, the Tucson Arena, the Leo Rich Theater, the Tucson Music Hall and Eckbo plaza and fountain.
The board also voted to proceed with a $126 million financing plan that will earmark about $70 million for the renovations and any contingency costs that could emerge, and refinance nearly $48 million in debt for the Rio Nuevo district. The funds will also establish an $8 million debt service reserve.

The list of improvements includes the following and can be downloaded: TCC Capital Improvement Project (CIP) Budget and TCC CIP Map.

Current commitments – $8.5 million
  • Ice Plant – Full replacement of Arena Ice Floor and Ice Plant, $3.2 million
  • Lot A Garage – 300-space parking garage in parking Lot A, $5.2 million
  • Parking Expansion – 45 additional spaces on site, $45,000
Convention Center priorities – $14.7 million
  • TCC – Renovation of Convention spaces and existing meeting rooms, $7.6 million
  • Arena – Lighting upgrades, $220,000
  • Site – Streetscape and Connections – Required UDC compliance for accessibility and screening, $2.5 million
  • Eckbo Historic Landscape Restoration – Upper Plaza to complete Church Streetscape upgrades, $1.9 million
  • Technology Enhancements – High speed data infrastructure throughout, $2.5 million
Meeting room expansion – $9.2 million
  • Convention Center Meeting Room Addition – West Entrance and 18,000 square feet of Meeting Rooms adjacent to Ball Room and South Ex Hall, $9.2 million
Entertainment priorities – $26.9 million
  • Lot C Garage – 500 stalls in Parking Lot C, $11.4 million
  • Music Hall Renovation – Renovation including restrooms, lobby, production lighting/sound, and new seating, $6.6 million
  • Music Hall Upgrades – Outdoor event patio and interior VIP area, $780,000
  • Leo Rich Renovation – Renovation including restrooms, lobby, production lighting/sound, and new seating, $2 million
  • Eckbo Historic Landscape Restoration – Central Plaza and North Walkway, $6.1 million

 

Related News

August 1, 2019
Tucson Convention Center Getting $65 million Upgrade, Expansion
June 25, 2019
Rio Nuevo Accepts Priority List For $65M in TCC Improvements
May 30, 2019
Architects Present Plans for $60 Million in TCC Improvements
December 12, 2018
Rio Nuevo Agrees to Participate in Volvo Site Project
November 14, 2018
Rio Nuevo Board Considers Up to $50M Investment into TCC
May 16, 2018
Tucson Roadrunners’ Improbable, Fast-Tracked Inception has them Poised for Success
February 21, 2017
23 New or Renovated Venues Looking to Lure This Year’s Top-Selling Tours
May 17, 2016
Council OKs Lease Agreement to Bring Hockey Team to Tucson
May 16, 2016
Tucson Proposing 10-year Deal with Minor League Hockey Team
April 26, 2016
Rio Nuevo will Spend $3.2M to get Arena Ready for Pro Hockey
February 20, 2015
Mejores Experiencias
April 10, 2014
Renovations of TCC Arena Marks New Era for Rio Nuevo

Related Documents

RFQs, RFPs, IFBs

September 18, 2019
RN-TCC-2019-09-03 Responses to RFQ Inquiries 9-18-19
September 3, 2019
RFQ CMAR Services for the Construction of Multiple Capital Improvement and Renovation Projects at the Tucson Convention Center
January 14, 2016
Addendum No. 1 – Fixed Audience Seating 14-01-16
July 30, 2014
Addendum No#140104
July 21, 2014
Invitation for Bids for Integrated LED Video Displays
January 9, 2014
Invitation for Bids for Folding Seats
January 9, 2014
Invitation for Bids for Fixed Audience Seating
September 10, 2013
RFQ Notification for CM@R Solicitation

Agreements

March 28, 2019
TCC Arena Floor & Ice Machine Design Build Contract

Rio Nuevo Documents

November 8, 2018
TCC Capital Improvement Project List

Notice of Expenditures

August 26, 2016
Notice of Expenditures Coyotes